Market Watch · The Docket
Updated November 2, 2026
November 2026. Major residential approvals include Winslow Park and The Shoals; St. Mary’s heart and neuroscience addition is under construction. Project stages are based on the cited records.
Purple dots mark park and land context, separately filtered from projects. Project dots are filled when construction has started, solid ring when approved, dashed when only filed. Light dotted rings mark proposed concepts. Tracts large enough to see are shown as a shaded circle of their stated acreage, centered on the project; it shows size, not the property line. Dots mark matched parcels, campus areas, subdivision areas, a sampled residential lot, or UGA project areas. The two October 27 additions use Census address matches; the NoDA pin marks the parent redevelopment address rather than the Phase 2 footprint. Some cover only part of a wider project or an announced tract; open the pin for its location basis. They are site context, not surveyed building footprints. Purple park/land pins use an identified address or a source's marketing coordinate; some mark an existing facility within a park rather than available land. Open each pin for its precise limits. November 2 additions use Census address matches: the Winslow Park and Shoals pins sit at one address within much larger tracts. Click a dot or a project for its status and source. The map contains 32 construction and concept projects and 11 separately filtered park and land markers. Only the 32 projects appear in the construction table. Park markers do not establish availability or construction. Highway 72, Gateway and other sites with unresolved locations are described below.
November 2026 · updated November 2
Winslow Park on Atlanta Highway was approved in June 2025 for roughly 900 homes, townhomes and apartments. The Shoals off Barnett Shoals Road was approved in March 2025 for up to 745 residences. Together with downtown student housing and active institutional investment, these plans shape the region's development pipeline.
The table covers 32 major projects, including Winslow Park, The Shoals and a $35 million heart and neuroscience addition at St. Mary's Hospital. Additional proposals appear below with their reported stages and sources.
Significant approvals, proposals and construction activity, with project stages as documented in cited records.
Winslow Park Approved
4500–4530 Atlanta Highway and Bedgood Road, west Athens
D.R. Horton plans to build the homes on land owned by Walton Georgia. The developer filed a regional-impact review in August 2024 for 874 homes on 207 acres (Walton). The Planning Commission tabled it in January 2025, when the plan was 944 units (Flagpole). Commissioners approved it unanimously in June 2025 against staff and Planning Commission advice; Athens Politics Nerd reports 396 houses, 216 townhouses and 313 apartments (Athens Politics Nerd). We have not yet read the ordinance's approved maximum, so the table says "reported." We found no permit or start; Athens-Clarke does not publish permits by project.
The Shoals Approved
Around Dekle Lake off Barnett Shoals Road, east Athens
This replaces the older Lakewood plan on the same land. Commissioners approved the revised planned development 7-2 on March 4, 2025: 575 to 745 homes of several types and at least 20,000 square feet of commercial space, with a mile of greenway (Athens Politics Nerd). Mallory & Evans later described a $95 million first phase of 285 residences, delivering in 2027 (REBusiness). We have not confirmed a construction start. Homes already built in earlier Lakewood phases are not counted.
St. Mary's Center for Heart, Vascular and Neurosciences Started
St. Mary's Hospital, 1230 Baxter Street
A 15,000-square-foot addition costing about $35 million is under construction, with completion expected in fall 2027 (St. Mary's; Healthcare Design). The same announcement describes a $13.6 million, 20,000-square-foot medical office near Presbyterian Village on Hog Mountain Road in Oconee, opening this fall. Oconee permits for a shell and interior finish at that location probably match it; the permit correspondence remains unconfirmed, and the proposal is described below.
D. Williams Road industrial park, Madison County Approved (land, not a project)
184 D. Williams Road, Commerce
Commissioners rezoned about 116 acres from agricultural to industrial on September 14 for a 13-lot park, lots of 5 to 21 acres (Main Street News). No tenant is named and no lots are marketed. It appears in the land layer below, not the project table.
Oconee permits we had read but not recorded. October's Oconee permit review found smaller commercial projects that never made it into our register: office buildings on Champions Way, Rhino Mini Storage on Moreland Heights Drive (about 50,000 square feet), a JenHill storage building on Hidden Hill Court, a $3.1 million restaurant on Jamestown Boulevard, a fuel store on Exchange Street and medical offices on Luxury Drive and Lampkin Branch Drive (county permit reports). A permit is permission, not proof of work. They are now in the register and below the table's size thresholds, except the storage project, which we are leaving out of the table until we see work.
West Broad, Finley and Reese. The Planning Commission minutes for October 1 record a 5-4 recommendation after the chair broke a tie, with the land-use change passing 5-3. The commission's public hearing is on its November 4 agenda.
Judicial Center. Commissioners approved an alternate design 7-3 on October 6 that keeps the "moon tree" and reduces parking on site. Urban Redevelopment Agency revenue bonds and parking-deck design are on the November 4 agenda.
Westclox and US 29 North. The Planning Commission recommended both in September (minutes). The October 6 commission agenda would not open for us, so the final votes remain unconfirmed.
Pine Woods and Country Corners. The Planning Commission approved both special uses on August 6; Country Corners' owner expects to add about 40 homes a year (minutes). We are confirming that the Planning Commission is the final authority for these.
College Avenue (former Quality Block). Recommended unanimously August 6. The September 1 commission vote is unconfirmed.
Barnett Shoals and Forest Road. A cottage-court planned development on 4.8 acres was recommended unanimously October 1 and goes to the commission November 4.
Madison Fields. The county planning commission recommended a preliminary plat in December 2025: 147 lots on 588.7 acres, conditioned on state approval of a community sewer and a traffic study (Main Street News). The developer's own site says 300 acres; we have not reconciled the two.
Publix at Oconee Station. Oconee's case archive shows the two supporting rezonings approved April 1, 2025. The developer reported a signed lease in January. We still have not found a building permit through the October 15 report.
This month we started a full register of industrial parks and land: 28 entries, 11 shown on the map. Most are carried from October. New this month are the D. Williams Road park in Madison County, two Old Elberton and Voyles Road listings in east Athens, an 8-acre industrial listing on Mars Hill Road in Oconee and a pad-ready grading plan on McClung Road. A listing is a dated claim, not a vacancy certificate, and none of these acres is added to a supply total.
| Park / site | Public role | What is there / going in | Available / next check |
|---|---|---|---|
| Athena Industrial Park Athena / Olympic / Voyles corridors, Clarke County Established industrial district; mixed ownership | County-promoted; ownership and authority involvement vary by parcel. | Existing: County inventory lists Carrier, Boehringer Ingelheim, Nakanishi, SKAPS and other manufacturers. Incoming: Meissner campus phases are tracked separately in the project table. Duckshin identifies its U.S. factory at 1805 Olympic Drive; opening date remains unconfirmed. | County advertises 1,200+ acres remaining, an undated aggregate not reconciled to current parcels or commitments. Individual offerings below are not additive to it. County park inventory · Duckshin factory address |
| Athens Commerce Park Commerce Boulevard / Jennings Mill Parkway, Clarke County Established business park | County-promoted; park-wide public ownership or management not established. | Existing: County describes more than 50 businesses across more than 100 acres. Incoming: No new tenant or construction phase confirmed in this park pass. | County features 180, 325 and 355 Commerce Boulevard. Current commitments and available area need confirmation. County park inventory |
| Coggins Industrial Business Park Ben Burton Road area, west Athens-Clarke Established business park | County-promoted; public ownership or management unconfirmed. | Existing: County describes a park for small and medium businesses; broker identifies 190 Ben Burton Road as within it. Incoming: No new tenant or active phase established in this pass. | Building and lot availability require a current listing check; no park-wide vacant-acre figure accepted. County park inventory · Park address context |
| Invista industrial tract Old Elberton / Pittard / Voyles roads, Athena area About 279 acres marketed; acreage discrepancy | County-branded marketing with a private broker; public ownership not established. | Existing: Marketed land adjacent to the RWDC operating site; the two properties are distinct. Incoming: No committed incoming tenant established. | County-branded listing updated June 25 gives 278.29 acres in its title and 278.90 in details. Confirm current offering and net usable area; do not include the adjacent RWDC plant. County-branded property listing |
| Olympic Dr industrial tract / 775 Olympic Drive 775 Olympic Drive, Clarke County 37.84 acres marketed | County-branded listing; private broker representation, title unverified. | Existing: Marketed industrial land within Athena Industrial Park. Incoming: Building-pad concepts are marketing possibilities, not evidence of construction or tenants. | Listing updated March 2 advertises sale and subdivision potential. Older material gives 36.1 acres; counted as one provisional tract, not two offerings. County-branded property listing |
| 125 Olympic Court industrial land 125 Olympic Court, Clarke County 13.92 acres marketed | Private broker listing; public ownership not established. | Existing: Broker markets wooded land zoned Employment-Industrial, parcel 221 016. Incoming: No tenant, permit or construction start established. | Marketed at $520,000. MLS history reaches June 2026, so a recent repost is not a new project announcement. Verify usable area, utilities and current commitments. Broker / MLS listing · Crexi listing |
| Athens-Ben Epps Airport hangar lease 1060 Ben Epps Drive, Athens-Clarke RFP 26032; lease footprint unconfirmed | County-issued airport land-lease solicitation. | Existing: Operating public airport. Procurement copies describe a hangar development opportunity. Incoming: August solicitation sought a land lease for a hangar; a copy describes demolition and replacement. Award and physical work unconfirmed. | Reported deadline October 14 has passed. This is a development lead, not a currently open offering. Official addenda and award still need review. Archived solicitation · Official procurement route |
| UGA Innovation Gateway incubator at CAGT 111 Riverbend Road, Athens University incubator / laboratory facility | University facility, distinct from a city-owned industrial park. | Existing: UGA houses incubator space within its Center for Applied Genetic Technologies, part of the wider innovation ecosystem. Incoming: Current resident roster and expansion plans have not been reconciled. | Available laboratory and office space, eligibility and lease terms need confirmation; whole-building area is not vacancy. UGA facility and location · UGA Innovation District |
| Watkinsville Industrial Park Industrial Boulevard / Greensboro Highway, Watkinsville Established industrial park; potential backfill | Private occupants/owners; park-wide city ownership not established. | Existing: Established manufacturing area including IMI's historic campus. Incoming: IMI's planned move to Gateway is a separate project; its current construction and relocation dates need checking. | City's November 2025 plan anticipated more than 100,000 SF becoming available after relocation. This is potential backfill, not confirmed current vacancy. City strategic plan, November 2025 · IMI historic campus |
| Madico Industrial Park / Madico Drive Highways 98 and 172, Comer area, Madison County 3.18-acre authority-marketed parcel; park context | Development authority markets land; parcel title and reservations require checking. | Existing: Established named industrial park; distinguish it from MadiCo West near Commerce. Incoming: No new tenant commitment established in this pass. | Authority advertises a 3.18-acre Madico Drive tract; May minutes discuss pricing without establishing a final price. Madison authority inventory · Park address context |
| D. Williams Road industrial park 184 D. Williams Road, Commerce (Madison County) About 116 acres rezoned; 13 lots planned | Private owner (D. Williams Properties LLC); no authority role established. | Existing: Agricultural land rezoned for industry; no existing industrial tenant identified. Incoming: Commissioners approved A-1 to industrial on September 14, 2026 for a 13-lot park with lots of 5 to 21.12 acres, a 100-foot setback and an emergency-only second entrance. | No lots are marketed yet and no tenant is named. A rezoning is not available, serviced land; utilities have not been confirmed. Main Street News, September 2026 |
Land that was refused. In October 2025 commissioners unanimously denied a request to rezone about 230 acres of greenbelt off Old Elberton Road for industry; the applicants had shown more than 2 million square feet of buildings (Red & Black). The Athena park nearby still advertises more than 1,200 acres remaining, an undated county figure (county inventory).
Madison IDBA Highway 72 park. Rezoned in June for light industry, about 72 acres combined; access work was complete except striping in August. Remaining lots and tenants are unconfirmed.
Gateway / IMI, Oconee. The county case archive records modified conditions for Industrial Properties Management at 1355 Aiken Road (40.56 acres) in April 2025, probably IMI's planned campus. We treat it as the same project, not a second one.
The major road projects that change access, not every repaving or signal. Stages run from planned (in a study or long-range plan, no construction money) to funded, let, under construction and open. Road plans are context, kept out of the project table, its totals and the map.
| Road plan | Stage | What and when | Why it matters | Source |
|---|---|---|---|---|
| SR 316 freeway conversion: Jimmy Daniell, Virgil Langford and Oconee Connector SR 316 between Bogart and the Oconee Connector, Oconee County | Under construction | Three at-grade crossings become grade-separated. Jimmy Daniell gets a diamond interchange with two roundabouts; Virgil Langford goes over SR 316 with no access to it; SR 316 flies over the Oconee Connector with ramps. One $139.4 million design-build contract (Archer Western, awarded November 2024). Timing: Jimmy Daniell has been closed at SR 316 since September 14 for about six months. Connector lanes were cut to two each way on September 18 until the bridges are done. Work is projected through at least the end of 2028. | Part of GDOT's plan to make SR 316 a freeway from I-85 to Athens. It serves Research Quarter, Epps Bridge and west Oconee, and it removes direct highway access from some side roads. | Oconee County Observations, October 2026 · Oconee County Observations, September 2026 · WUGA, January 2025 Checked Nov 2, 2026 |
| SR 316 at Dials Mill Extension SR 316 in western Oconee County, near the Barrow line | Let | A full interchange at Dials Mill Extension. Dials Mill Road itself is to end in cul-de-sacs on each side of SR 316. Contract of $26.4 million to GP Construction. Timing: The county chair said in March that construction would start within weeks. We have not confirmed a start. | The westernmost Oconee access to the future freeway. | Oconee State of the County, March 2026 · GDOT SR 316 study, November 2025 Checked Nov 2, 2026 |
| Watkinsville truck bypass (GDOT PI 0017970) SR 15 to US 441 around downtown Watkinsville, Oconee County | Funded | A new two-lane route to take trucks out of downtown. GDOT showed three alternatives in April, reported at roughly 1.8 to 2.9 miles. Commissioners resolved in May against any route through protected farmland and asked for more study. Timing: County chair said funding is in place and right of way could start in 2026. The alignment is not chosen. | Changes truck access south of Watkinsville and the value of land along whichever route is picked. | GDOT public meeting layouts, March 2026 · Oconee Enterprise, May 2026 · Oconee State of the County, March 2026 Checked Nov 2, 2026 |
| North Avenue rebuild North Avenue from Willow Street to Collins Industrial Boulevard / Freeman Drive, Athens | Funded | A $25 million federal RAISE grant. Commissioners approved the four-lane safety concept 8-1 on June 2: five lanes down to four, with a multiuse path and safer crossings. Timing: Federal highway officials extended the grant deadline in May. Construction dates not published. | Less car capacity, more walking and biking on the north gateway to downtown, near the Hilltop and NoDA projects. | Athens Politics Nerd, 2026 ordinances · Flagpole, May 27, 2026 · MACORTS FY 2024-2027 TIP Checked Nov 2, 2026 |
| TSPLOST 2026 program, Athens-Clarke Countywide, Athens-Clarke | Funded | $239 million approved by voters May 19. The largest named lines: Eastside Athens complete streets ($11.0 million), Winterville intersections ($9.8 million) and North Avenue / Loop 10 bridge work ($7.3 million). Mostly repair, safety and multimodal work, not new lanes. Timing: Collections begin October 2027 and run six years. An implementation plan is on the November 4 commission agenda. | Sets the county's road spending through 2033; watch the implementation plan for timing by corridor. | ACC TSPLOST 2026 · ACC Commission agenda, November 4, 2026 Checked Nov 2, 2026 |
| SR 316 at McNutt Creek Road SR 316, west Oconee County | Planned | Right-in, right-out access instead of the full interchange once shown. GDOT program cost $17.2 million. Timing: County lists 2027. GDOT's 2025 study said funding for its phases was still being determined. | Limits turning access for land along McNutt Creek Road. | GDOT SR 316 study, November 2025 · Oconee State of the County, March 2026 Checked Nov 2, 2026 |
| SR 316 at Mars Hill Road and Julian Drive SR 316, west Oconee County | Planned | Mars Hill Road closes at SR 316 with cul-de-sacs. Julian Drive gets an access road to US 78 instead of a crossing. Timing: County lists 2030 for both. Funding not yet determined in GDOT's study. | Two more side roads lose direct highway access; traffic shifts to the interchanges. | GDOT SR 316 study, November 2025 · Oconee State of the County, March 2026 Checked Nov 2, 2026 |
| SR 316 at SR Loop 10 Eastern end of SR 316 at the Athens Perimeter, Oconee and Clarke | Planned | A major upgrade of the junction where SR 316 meets Loop 10. Study cost figures conflict, from about $121 million to $221 million. Timing: County lists 2032. Funding not yet determined. | The last at-grade piece between the freeway and the Perimeter, next to Research Quarter and Epps Bridge. | GDOT SR 316 study, November 2025 · Oconee State of the County, March 2026 Checked Nov 2, 2026 |
| US 441 widening, Oconee segment, and a Bishop bypass US 441 south of Watkinsville through Bishop, Oconee County | Planned | Widening of US 441 in Oconee County, with a bypass of Bishop. Timing: GDOT shows 2028 construction for the widening; the county chair expects significant delay. Bishop bypass design starts in 2029. | The south Oconee route to I-20 at Madison. Long-promised; treat dates as soft. | Oconee State of the County, March 2026 Checked Nov 2, 2026 |
Our read: SR 316 is the road plan that matters most here. When the work is done, the west side will have a freeway to I-85 in Gwinnett, and the Research Quarter and Epps Bridge area sits at its end. The east side does not get the same lift. The Athena park's industrial land still reaches I-85 by Loop 10 and US 29, roughly half an hour away, and we found no program to change that. Several Oconee side roads will lose direct access to SR 316, so land along them will depend on the interchanges.
Credible public leads without a confirmed status, count or location. They are not in the table or its totals.
| Project / location | What is public | Source |
|---|---|---|
| Newton Bridge Road subdivision 610–760 Newton Bridge Rd, Athens | Preliminary plat for 277 lots on 123 acres in plans review in March. A 2025 proposal showed 346 homes and townhouses. The rezoning outcome has not been read. | ACC plans review, March 19 |
| Newton Bridge Crossing 1125 Newton Bridge Rd | D.R. Horton markets homes; Planning Commission recommended a condition change in July referencing 62 homes. | PC minutes, July 2 |
| Township at Jennings Mill 290 Classic Rd | Plat for a public road serving a new multifamily development. Size unknown. | ACC plans review, March 19 |
| Homewood Hills redevelopment Jefferson Rd, 16 acres | Two five-story apartment buildings and townhomes. The commission delayed its vote in December 2025 to January; the outcome is unconfirmed. | Athens Politics Nerd |
| Senior and affordable rezonings 155 Whit Davis Rd; 1165 Oglethorpe Ave; 4320 Atlanta Hwy | Recommended April and August with 55+ or income limits. Unit counts and final votes unconfirmed. | PC April 2 · PC August 6 |
| Other residential rezonings 4190 Lexington Rd; 1930 New Jimmie Daniel Rd | Recommended in April. Units unknown. | PC April 2 |
| 1095 W Broad St | Five-story building with three floors of apartments over parking and shops, in plans review November 5. | ACC plans review |
| Industrial plans 5378 Atlanta Hwy; 330 Old Hull Rd; 1385 Winterville Rd | A new warehouse in plans review; a concrete batch plant approved April 7; new walls at a ready-mix terminal. | Plans review · WUGA |
| Public works, Athens-Clarke | Fire Station #5 on 7.5 acres at 4730 Old Lexington Rd; Holston Elementary gym addition in plans review. The North Avenue rebuild is now under Road plans. | Nov 4 agenda · APN |
| UGA projects | West Campus dining and learning center ($60.7 million, due fall 2026); Creswell Hall restoration ($115.7 million, 2027); a football facility on the old track site (2027); a 565-bed first-year hall due this year. Current stages not rechecked. | UGA · capital list |
| St. Mary's medical office, Presbyterian Village Hog Mountain Rd, Oconee | 20,000 SF, $13.6 million, opening fall 2026 per the owner. Probable permit match not confirmed. | St. Mary's |
| Oconee leads | Experiment Station Road grocery and a 119-lot subdivision (rezonings approved January); QuikTrip on US 78; St. Aelred church in Bishop; Dawson and Heritage park expansions; Bishop Warehouse District Phase 2 approved in Watkinsville. SR 316 and the Watkinsville bypass are now under Road plans. | Case archive · Oconee County Observations |
| Madison leads | A proposed 50-acre subdivision in Comer; a solar lease at the county transfer station; a countywide data-center moratorium (September). | Main Street News |
Information current through: November 2, 2026, as supported by the cited records.
Area. Clarke, Oconee, Madison and Oglethorpe counties and the cities inside them. County subtotals are not comparable yet, so we do not add them up.
What the labels mean. A permit means permission to build. "Started" means an owner, contractor or public record reported physical work on the date cited. Delivery dates are targets. Passages marked Our read are our analysis.
Project stages distinguish proposals, approvals, permits and reported construction. Dates and scopes may change. Submit a project update.
The larger projects: 100 or more homes or apartments or 250 student beds, commercial sites of 50,000 square feet or 10 corridor acres, industrial investment of $10 million or 50 jobs, and institutional or public projects of $10 million or more, plus smaller ones that change a corridor or show where a market is heading. Major projects and sites across Clarke, Oconee, Madison and Oglethorpe are covered, with project-specific sourcing.
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Hub Athens Dougherty 295 E Dougherty St, Athens | 536 units; 1,656 beds; ground-floor retail and a public parking deck | Started Core Spaces announced its groundbreaking in July 2026; completion targeted for 2028. The commission approved the land swap 6-4 in January 2026. | Jul 2026 | Multifamily Dive, July 31, 2026 Contractor project page Athens Politics Nerd, January 2026 | Oct 26, 2026 |
| Magnolia 1000 W Broad St (Broad and Milledge), Athens | 179 student apartments over a Publix | Started Northwood Ravin reports construction under way and preleasing open; delivery set before the 2027-28 school year. The Publix is reported open. | Oct 2026 | Northwood Ravin, October 7, 2026 | Oct 26, 2026 |
| Hilltop Athens 218 North Ave, Athens | 222 beds | Started Morrison Avenue reported construction under way in May 2026; fall 2027 target. Stage as of May. | May 2026 | Morrison Avenue release, May 12, 2026 | Oct 26, 2026 |
| West Broad, Finley and Reese apartments Block of W Broad, Finley, Reese and Pope Sts, Athens | 181 units; 425 bedrooms; 8 townhouses (as reported) | Filed Cardinal Group (reported). The Planning Commission recommended approval 5-4 on Oct 1, 2026, after the chair broke a tie; the land-use change passed 5-3. The Commission's public hearing is on its November 4 agenda (2.47 acres). | Oct 2026 | Flagpole, October 7, 2026 ACC staff report ACC Planning Commission minutes, Oct 1, 2026 ACC Commission agenda, November 4, 2026 | Nov 2, 2026 |
| 290 Lumpkin 290 S Lumpkin St at Wray St, Athens | 243 residences; 353 beds; retail and BCM ministry space | Started CCI's July 13 announcement reports construction began summer 2025. Current property website confirms 243 residences / 353 beds and summer 2027 move-ins. Earlier reports used different unit counts; opening remains a target. | Jul 2026 report | Current property website CCI announcement, July 13, 2026 REBusinessOnline, July 15, 2026 | Oct 27, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Horizon at Tallassee 888 Horizon Blvd, Athens | Apartment buildings 1300 and 1500 | Approved Building permits issued in 2025. Current stage not confirmed. | 2025 | ACC multi-family permit report, 2025 | Oct 26, 2026 |
| Talley Crossing 160 Talley Crossing, Athens | Apartment buildings 1 to 6 | Approved Building permits issued in 2025. Current stage not confirmed. | 2025 | ACC multi-family permit report, 2025 | Oct 26, 2026 |
| Heyward Allen Parkway apartments 200 Heyward Allen Pkwy, Athens | Apartment buildings 1000 to 6000 | Approved Building permits issued in 2025; owner names differ between rows. Current stage not confirmed. | 2025 | ACC multi-family permit report, 2025 | Oct 26, 2026 |
| The Grove senior living 1641 Virgil Langford Rd, Oconee County | Detached senior homes; dozens of unit permits since January 2025 | Approved Building permits issued in phases, January 2025 to February 2026, plus a clubhouse. Unit total not yet reconciled. | Feb 2026 | Oconee permit report, Jan 31, 2025 Oconee permit reports | Oct 26, 2026 |
| The Landing assisted-living expansion 2881 Monroe Hwy, Bogart | 32,849 SF addition; $6.0 million permit | Approved Rezoning modification approved Oct 7, 2025; building permit issued Aug 20, 2026. Part of the campus that includes Standard of Bogart. | Aug 2026 | Oconee County case archive Oconee permit report, Aug 20, 2026 | Oct 26, 2026 |
| Celebration Village Athens Oconee Connector at Dowdy Rd, Oconee County | About 61 acres; assisted living, memory care and cottages | Approved Rezoned 2020; groundbreaking held 2025. Commissioners denied the developer's phasing appeal Sept 1, 2026. No vertical building permit matched in the incomplete report set reviewed. | Sep 2026 | Oconee County case archive County memo, Aug 27, 2026 | Oct 26, 2026 |
| Westland Rivercrest and Riverwood Drs, Oconee County | New homes, Phase 2-B (D.R. Horton) | Approved Home building permits issued through September 2026. | Sep 2026 | Oconee permit report, Sept 2026 Oconee permit report, July 2026 | Oct 26, 2026 |
| Willow Creek Willow Creek Dr, Oconee County | New homes (Lennar) | Approved Home building permits issued through July 2026. | Jul 2026 | Oconee permit report, April 2026 | Oct 26, 2026 |
| Malcom Bridge Estates Malcom Estates Dr and Rdg, Oconee County | New homes (several builders) | Approved Home building permits issued through September 2026. | Sep 2026 | Oconee permit report, Sept 2026 Oconee permit report, March 2026 | Oct 26, 2026 |
| The Square at NoDA (North Downtown Athens Phase 2) Former Bethel Midtown Village, Hickman Dr, Athens | 146 apartments (reported); part of a four-phase redevelopment | Started Grady Newsource reports Phase 2 construction continuing October 15, with completion targeted for end-2027. Phase 1, The View, was completed in 2025 and is not counted in this row. | Oct 2026 | Grady Newsource, October 15, 2026 Jonathan Rose Companies project page | Oct 27, 2026 |
| Winslow Park 4500-4530 Atlanta Hwy and Bedgood Rd, west Athens | Reported 925 homes, townhomes and apartments on about 207 acres; counts differ by source | Approved D.R. Horton is to build the homes on Walton Georgia land. Commissioners approved the rezoning unanimously in June 2025 against staff and Planning Commission advice. Athens Politics Nerd reports 396 houses, 216 townhouses and 313 apartments; earlier figures were 944 (Flagpole, January 2025 proposal) and 874 (Walton, 2024). We have not read the ordinance's approved maximum or found a permit or start. Address point. | Jun 2025 | Athens Politics Nerd, June 10, 2025 Walton Global, August 2024 Flagpole, January 8, 2025 | Nov 2, 2026 |
| The Shoals (Barnett Shoals Road) Around Dekle Lake off Barnett Shoals Rd, east Athens | Up to 745 homes and apartments; at least 20,000 SF commercial | Approved Commissioners approved the revised planned development 7-2 on March 4, 2025, replacing the older Lakewood plan. Mallory & Evans reported a $95 million first phase of 285 residences with deliveries in 2027. Construction start not confirmed. Earlier Lakewood phases already built are not counted. Address point at the master-application address. | Mar 2025 | Athens Politics Nerd, March 7, 2025 REBusiness, October 1, 2025 | Nov 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| UGA School of Medicine building Health Sciences Campus, Prince Ave, Athens | Three floors | Started University reports construction continuing; dedication planned for December 2026. | Aug 2026 | UGA, August 14, 2026 | Oct 26, 2026 |
| UGA Science and Ag Hill, Phase III Building 1013, south campus, Athens | Classroom building renovation | Started University reports construction under way; opening expected spring 2027. | Aug 2026 | UGA, August 14, 2026 | Oct 26, 2026 |
| Piedmont Athens Regional surgical expansion 1199 Prince Ave, Athens | $56 million; two new operating rooms and a hybrid OR; eight phases | Started Piedmont reported the start in September 2025; phases run through 2028. | Sep 2025 | Piedmont, September 16, 2025 | Oct 26, 2026 |
| Medical office Building 400 1305 Jennings Mill Rd, Oconee County | 45,985 SF; $12.2 million interior-finish permit | Approved Building permits issued: shell January 2026, interior finish March 30, 2026, sign August 2026. | Aug 2026 | Oconee permit report, March 30, 2026 Oconee permit report, Sept 2026 | Oct 26, 2026 |
| Resurgence Drive medical office 1780 Resurgence Dr, Oconee County | 42,605 SF shell; tenant buildouts | Approved Shell permit March 2025; tenant buildout permits through March 2026. | Mar 2026 | Oconee permit report, March 2025 Oconee permit report, March 2026 | Oct 26, 2026 |
| Research Quarter expansion (Wellstar lots) Virgil Langford Rd at SR Loop 10, Oconee County | Park requested cap of 250,000 SF on 22.6 acres; Wellstar Health System owns three lots | Approved County reported approval of P26-0122 in August 2026 with ten conditions; final condition text remains unchecked. Local reporting describes a hospital on the concept plan; this review has not confirmed a Wellstar commitment. | Aug 2026 | Oconee County staff report, July 9, 2026 Oconee County Observations, July 27, 2026 County August 4 meeting highlights | Oct 26, 2026 |
| Prince Avenue campus 2201 Ruth Jackson Rd and 3691 Monroe Hwy, Bogart | School gym 28,611 SF ($6.9 million); church Phase 1 remodel 34,226 SF ($8.9 million) | Approved Building permits issued January 2025 (gym) and July 9, 2026 (church remodel). | Jul 2026 | Oconee permit report, January 2025 Oconee permit report, July 2026 | Oct 26, 2026 |
| Grace Fellowship Church 1150 Malcom Bridge Rd, Oconee County | 32,725 SF sanctuary and offices; $7.0 million permit | Approved Foundation permit February 2025; building permit June 17, 2025. | Jun 2025 | Oconee permit report, June 2025 | Oct 26, 2026 |
| Athens-Clarke Judicial Center 120 W Dougherty St, Athens | 218,215 SF; estimated $225 million concept | Approved The Commission chose the site and concept in June and approved an alternate design 7-3 on Oct 6 that keeps the 'moon tree' with less on-site parking. Urban Redevelopment Agency revenue bonds, change orders and parking-deck design are on the November 4 agenda. Tentative new-building start early 2028. | Oct 2026 | ACC project update, October 8, 2026 Athens Politics Nerd, 2026 ordinances ACC Commission agenda, November 4, 2026 | Nov 2, 2026 |
| St. Mary's Center for Heart, Vascular and Neurosciences St. Mary's Hospital, 1230 Baxter St, Athens | 15,000 SF addition; about $35 million | Started St. Mary's reports construction under way on the addition to its emergency and outpatient surgery building, with completion anticipated in fall 2027. | Sep 2026 | St. Mary's / Trinity Health release Healthcare Design, September 1, 2026 | Nov 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Athens Athletic Club 1660 Plaza Pkwy, Oconee County | 57,117 SF club; $12 million permit | Approved Building permit issued March 2, 2026; spas March 27. Site grading reported in June. County approved medical offices in place of a planned hotel on the same site July 7, 2026. | Jul 2026 | Oconee permit report, March 2, 2026 Oconee permit report, spas, March 27, 2026 Oconee County case archive Oconee County Observations, June 5, 2026 | Oct 26, 2026 |
| Westclox overlay 100 and 130 Newton Bridge Rd, Athens | 19.48 acres of a 2021 development; commercial first, housing allowed after | Filed Planning Commission recommended the overlay 6-0-1 on Sept 3, 2026, with 3 acres of open space and a Dairy Pak Road path. Final commission vote not confirmed. The 234,272 SF former Westclox factory sits vacant. | Sep 2026 | ACC staff packet, October 6, 2026 ACC Planning Commission minutes, Sept 3, 2026 | Nov 2, 2026 |
| US 29 North retail rezoning 1295 US 29 Hwy N, Athens | 2.38 acres; plan shows 19,600 SF of retail (not binding) | Filed Planning Commission recommended approval unanimously Sept 3, 2026, with sidewalks and Commercial-Rural uses only until sewer arrives. Final commission vote not confirmed; the October 6 agenda could not be read. | Sep 2026 | ACC staff packet, October 6, 2026 ACC Planning Commission minutes, Sept 3, 2026 | Nov 2, 2026 |
| Athens Arena District (proposed master plan) Around Akins Ford Arena / Classic Center; Foundry, Hickory, Willow and East Broad streets, Athens | Proposed hotel, housing, parking and entertainment/public-space program | Proposed Public master-plan concepts; district framework and parcel concepts pending approval in the September presentation. Approximate context pin at the Classic Center address, not a parcel boundary or proposed building footprint. | Sep 2026 | County-posted Arena District presentation, September 2, 2026 | Oct 27, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Meissner campus Spring Valley Rd area, Athens | $250 million campus announced 2023; about 1,700 jobs planned | Approved Development authority bonds approved 2023. Meissner held a ribbon cutting for its X-ray facility and a groundbreaking for the manufacturing phase in 2026; sustained construction not yet confirmed. | 2026 | Meissner, 2026 Flagpole, April 4, 2023 | Oct 26, 2026 |
Proposed means a publicly described concept or master plan; it does not establish a formal application, approval or construction start. Filed means an application or planning recommendation. Approved means a recorded approval or issued permit; the row names the step. Started means physical work reported by an owner, contractor, institution or public record on the date cited. The verification date records a source check, not a fresh inspection or completion check.
Sources: Athens-Clarke County Mayor and Commission, Planning Commission and permit reports; Oconee County Board of Commissioners, the joint Oconee Planning Commission, the county case archive and weekly permit reports; county staff reports; University of Georgia and Piedmont announcements; developer and contractor releases; and local reporting, which we cite by name. From November: Athens-Clarke Planning Commission minutes and weekly plans-review agendas, Watkinsville council minutes, Madison County commission packets and local reporting, hospital and university releases. Road plans: GDOT project pages and lettings, the MACORTS Transportation Improvement Program and long-range plan, and the Athens-Clarke TSPLOST program. Agendas and minutes are the primary record; press coverage fills in announcements and groundbreakings. We report what the record says and label what is not yet confirmed. This report is updated through the month; each month gets a new report.
See something we missed or got wrong? Tell us. How Redchip researches and verifies: Method.
Disclosure: the author is a partner in Vanguard Industrial Partners, which develops projects in the Southeast and may pursue opportunities involving projects covered here. This report uses public sources; development discussions do not determine project inclusion or status. General information only; see the disclaimer.